Muni Metro Fix It! Week Improves Rail Service, Safety and Reliability

Muni Metro Fix It! Week Improves Rail Service, Safety and Reliability
By Jessie Liang

Overhead Line crew replacing wire and custodians cleaning metro station

Overhead Line Department replacing wire and custodians cleaning metro station during Fix It! Week, April 19, 2022

A new quarterly effort to increase work time to accomplish necessary Muni Metro system maintenance in April 2022 was a resounding success. Here is a behind-the-scenes video recap. The maintenance initiatives aimed at making subway operations more reliable and preventing feature breakdowns. The maintenance teams were able to perform an entire month of work within the 10 days when subway service was substituted by bus service to provide SFMTA workers the extended Fix It! Week work window. 

Every night after Muni Metro subway service hours, SFMTA maintenance crews work to maintain the tracks and equipment underground. On most nights, this gives our teams only about two hours to get work done. During the first Fix It! Week, from April 14 to April 23, 2022, buses provided substitute service for Muni Metros lines and the subway between Embarcadero and West Portal was closed early for work to begin at 9:30 pm. These nightly early shutdowns gives SFMTA maintenance crews more hours to complete infrastructure improvement works underground that cannot be completed during the normal windows. 

The Fix It! Week provided 56 total work hours, during which several SFMTA teams completed over 2,000 hours of maintenance and inspections. On the busiest nights, the maintenance teams had up to 55 staff in the tunnel from West Portal to Embarcadero delivering safety improvements, station and tunnel enhancements, subway track and wayside equipment maintenance, and traction power upgrades.  

Each night during Fix It! Week, custodians from the Buildings and Grounds teams did deep cleaning at West Portal, Forest Hill, Castro, and Church stations, while the Maintenance Engineering staff was in the tunnel inspecting and collecting data. Stationary engineers from Mechanical Systems in various stations focused on safety enhancements such as installing new safety handrails at the platform ends, new ventilation for station agent booths, new pump covers, fire and life safety systems, and new electrical room ventilation.  

The Overhead Lines crew also used Fix It! Week to replaced 600 feet of wire at Castro Station while the Track Maintenance team brought two pieces of 1,500-pound stock rail in and out of the subway. The Motive Power crew replaced emergency battery systems and worked with all-electrical clearance holders to restore systems on time for rail service to restart as the Signal team removed legacy train control systems for future upgrades. The Underground team and the Paint Shop staff also contributed to this remarkable accomplishments. The Cable Car division, who had not previously participated in extended maintenance periods, did channel and conduit cleaning and checked and confirmed all wires were in good condition during the April Fix It! Week. 

Many people in the support team who were not doing the maintenance but coordinating the efforts all helped to make Fix It! Week successful. They ensured safety standards were being upheld, critical repair priorities were being addressed, and the subway was being reopened to restart rail service on time every day. 

Muni operations and transportation infrastructure are vital to San Francisco’s economic vitality, environmental sustainability, and cultural diversity. The FY 23 - FY 24 SFMTA Budget will continue to invest in infrastructure improvements to keep the Muni Metro system in a state of good repair. Thank you for your patience and understanding while we improve the safety, reliability and on-time performance of the Muni Metro system. 

The next Fix It! Week will be happening in August of 2022. 

For more information, visit the Muni Metro Maintenance Project page. 



Published June 06, 2022 at 11:09PM
https://ift.tt/EPO1dig

Comments

Popular posts from this blog

India's foreign exchange reserves reached a peak of $ 457.468 billion.

India's foreign exchange reserves reached a peak of $ 457.468 billion. India's foreign exchange reserves increased by $ 2.52 billion to reach its all-time high of $ 457.468 billion during the week ended December 27. India ranks 8th in the list of countries with the highest foreign exchange reserves in the world, China ranks first in this list. Foreign exchange reserves It is also called forex reserves or reserves of foreign exchange reserves in the balance of payments are called 'reserve assets' and are held in the capital account. They are an important part of a country's international investment position. This should include only foreign rupees, foreign bank deposits, foreign treasury bills, and short-term or long-term government assets, but includes special withdrawal rights, reserves of gold and reserves of the International Monetary Fund. It is more appropriate to call it an official international repository or international repository. Foreign e

Artificial intelligence (AI) is the simulation of human intelligence processes by machines, particularly computer systems.

Artificial intelligence Artificial intelligence (AI) is the simulation of human intelligence processes by machines, particularly computers. Typical applications of AI include expert systems natural language processing (NLP), speech recognition, machine vision and many more. AI programming focuses on three cognitive skills: learning, reasoning, and self-improvement. Learning process . This aspect of AI programming focuses on obtaining data and creating rules to convert data into actionable information. The rules called algorithms, provide computing devices with step-by-step instructions to accomplish a specific task . The process of reasoning. This aspect of AI programming focuses on choosing the right algorithm to reach the desired result. Processes of self-improvement. This aspect of AI programming is designed for consistently fine algorithms and ensures that they provide the most accurate results possible. Advantages and disadvantages of artific

12th Urban Mobility India Conference and Expo 2019 held in Lucknow

12th Urban Mobility India Conference and Expo 2019 held in Lucknow he 12th edition of Urban Mobility India Conference and Expo 2019 was held in Uttar Pradesh’s capital city Lucknow from 15th to 17th November 2019. It was organized by the Institute of Urban Transport (IUT), a professional body under the Union Ministry of Urban Development. The  theme  of this year’s conference was  “Accessible and liveable Cities” . About Urban Mobility India (UMI) Conference and Expo It is an annual flagship event organized under the aegis of Union Ministry of Urban Development. Its genesis is from the National Urban Transport Policy of the Government of India, 2006 (NUTP). Primary objective : To disseminate information to the cities and to help them keep up-to-date with the best urban transport practices. Other Objectives : To provide an opportunity for key decision-makers and delegates to interact with service providers, civil society, academia, experts, professionals, industry, technolo

Health Ministry sign MoC with Bill & Melinda Gates Foundation for technical support

Health Ministry sign MoC with Bill & Melinda Gates Foundation for technical support Union Ministry of Health and Family Welfare signed a memorandum of cooperation (MoC) with the Bill & Melinda Gates Foundation (BMGF) for technical support. Under this MoC, BMGF will provide technical, management and program design support to Union Health Ministry through its grantees as well as other partners. The special focus under MoC will be on innovation, best practices and enhancing performance management. Highlights of MoC BMGF will support the Health Ministry’s work towards strengthening primary health aspects. This includes reducing maternal mortality and child mortality, improving nutrition services as well as increasing immunization reach. It will also make efforts towards bolstering the entire health system by- Increasing access to family planning measures amongst younger women as well as reduce the burden of select infectious diseases such as Tuberculosis (TB), Visceral

5 Jobs that AI can replace in the next ten years

5 Jobs that AI can replace in the next ten years 1.  Customer relationship advisor The emerging chatbots have redefined the experience of customer care. The probability of all telemarketing jobs getting replaced by AI is the highest. One of the major reasons behind this is efficiency. AI-enabled chatbots are considered more efficient than human resource-driven customer care services. 2.  Programming language trainer All the IT firms employ a training consultant for various functions. The job of a programming language trainer is already on its way out. Employees prefer e-learning services over the human trainer. AI-driven interactive training solutions are likely to replace the job of programming language trainers. 3.  Proofreaders There is nothing innovative about this job role. Almost all blogging sites use proofreading applications and software. There is a high probability that this job role will get completely removed in the coming future. Companies are developing self-che